What can be done if the regulator delays a permit application?

In this special report, Gordon Wignall, a barrister specialising in environmental law at 6 Pump Court, examines the environmental permit process and what to do if a permit application is taking a long time.


SPECIAL REPORT: What can an operator do if the regulator is dragging its feet on an application for an environmental permit – far too common a story these days?

Perhaps the regulator has no intention at all of granting the application, perhaps it just does not have the know-how to determine the application within the time allowed, or perhaps it is just being too slow. Can, or should, the operator bring matters to a head, and what are the main risks if it does so?

Barrister Gordon Wignall, environmental law specialist

Time limit

The operator and the regulator can of course agree to extend the time allowed for a determination. However, in the current environment of cut-backs, it is quite possible that the regulator’s decision will not be made within the time limit prescribed by the legislature, especially since new non-statutory obligations and time-limits seem to be imposed at the ‘duly-made’ stage.

There may be other reasons why it looks as though the regulator’s decision will end up being postponed. For instance, the operator might start facing extensive requests for further information, or, following pre-application discussions, it may be clear that the regulator has little enthusiasm for the process involved. The regulator may not have ready access to the expertise required for a particularly novel application.

In these circumstances, the operator may need to make a judgment-call as to whether to let the process continue, or to bring to a head the issue of the regulator’s non-compliance with the relevant time-limit. Where the process involved is likely to give the operator a competitive edge, or where it is a reasonable assumption that the regulator will not issue the permit at all, then it may be better to challenge the non-determination.

This challenge is brought about by serving a notice of deemed refusal. This can be done at any time after the legislative date for the determination has passed.

There is much to be said for instigating an appeal against a deemed refusal

Appeal

The effect is then to engage the prescribed independent procedure, managed by the Planning Inspectorate (in England), PEDW (in Wales), DPEA (in Scotland) or PAC (in Northern Ireland).

In other words, the appeal process will be engaged, at the end of which, if the appeal is successful, the inspector has all the powers of the regulator and can direct the regulator to grant a permit. There is a long-stop of up to six months to start the appeal process (depending on the type of permit being sought).

The consequence of the initiation of an appeal is not that the regulator walks away from the process. The regulator will continue to engage, and the parties will continue to try and agree the points at issue between them. If necessary, the operator is likely to have to commission the services of an expert in order to help the inspector (for instance for pollution risks or acoustics).

It is important to note that if it comes to a full hearing, the inspector will not be making a determination as of the date of the service of the notice of deemed refusal (i.e. on the material available only as of that date). Since the inspector has all the powers of the regulator at the appeal, then he / she will have to consider the evidence presented at the hearing of the appeal. The inspector will have become the decision-maker.

It is sometimes forgotten that the Regulators’ Code itself should come to the aid of an operator (principle 1, for instance, being that “Regulators should carry out their activities in a way that supports those they regulate to comply and grow”).  National regulators have their own codes of conduct which will also require the regulator to engage.

In many circumstances, therefore, there is much to be said for instigating an appeal against a deemed refusal. It is better to start the appeal process than to risk the determination being dragged on for far too long. The drawback is any extra cost, for instance in obtaining assistance with the wording for the commencement of the procedure, or in obtaining expert evidence to assist the inspector in the event of the failure of continuing negotiations (which then operator should always promote).

Costs

Costs are rarely awarded at a final appeal, but where a strong appeal package can be submitted in advance to the regulator, then this is likely to be an inducement to the regulator to concede the appeal when accompanied by a warning that an application for costs may be made to the tribunal. There is absolutely no reason why the operator and the regulator should not hold a meeting on a without prejudice basis to find a mutual solution to the apparent obstacles to the grant of the permit, and also to agree its terms.

Where there are strong commercial reasons for putting a little pressure on a regulator, there is much to be said for serving a notice of deemed refusal in the expectation that an environmental permit will be granted more quickly than it would be if the process is left to stall.

Article submitted by Gordon Wignall.

Share this article with others

Subscribe for free

Subscribe to receive our newsletters and to leave comments.

Back to top

Subscribe to our newsletter

Get the latest waste and recycling news straight to your inbox.

Subscribe