Green light for 13m Merseyside MBT plant

Green light for 13m Merseyside MBT plant

A 13m MBT facility which will save around 1.5m in waste disposal costs each year in Merseyside has been given the go-ahead this week.

Knowsley council granted planning approval for the mechanical biological treatment (MBT) plant in Huyton Business Park, which will process around 50,000 tonnes of waste each year and create 23 jobs.

/photos/mersey2.jpg
The Huyton MBT plant will process around 50,000 tonnes of mixed waste each year

Plans for the project, which is a partnership between Merseyside Waste Disposal Authority (MWDA), Fairport Engineering, Defra, and the Northwest Regional Development Agency (NWDA), were first announced in December (see letsrecycle.com story).

The NWDA has contributed 2.1m to the 13m project and Defra's New Technology Demonstrator Programme has awarded 5.6m, with the MWDA also providing financial support.

Carl Beer, director of Merseyside Waste Disposal Authority (MWDA), said: “This is a great boost for the region’s waste management. The government is supporting this scheme with a lot of money because it believes the technology has potential to help councils across the country cut the amount of waste they send to landfill.”

Technology


The technology, developed by Fairport Engineering, a sister company of Orchid Environmental, will build the plant and operate it.

It will use an environmentally friendly, low-temperature heat treatment process, to convert non-hazardous household waste into renewable fuel.

Recyclables such as metals, glass, stone and mixed plastics, will be removed before the fuel conversion takes place.

Processing will take place in a sealed building and will have to comply with strict regulations on emissions.

There will be no chimney because special bio-filters, containing natural products including wood fibres, will filter out dust and emissions.


” The government is supporting this scheme with a lot of money because it believes the technology has potential to help councils across the country. “
– Carl Beer, MWDA

Fairport director Steve Whatmore said: “This award of planning consent reflects the confidence and enthusiasm in the region to see this new UK technology deliver urgently needed economic and environmental benefits.

“This has been made possible by addressing waste processing problems in a different and innovative way.”

Processing is expected to begin by the end of 2007, once the building has been modified, and the plant has been constructed.

The site has a previous use as a waste processing plant as fuel was produced there in the 1980s. It is also located next door to an existing waste transfer station.

The project is funded until April 2009 but if it is successful, will have a long-term future in MWDA's waste management plans.

The Knowsley site, is part of Defra's New Technology Demonstrator Programme, a scheme which has been criticised for delays in agreeing funding (see letsrecycle.com).

Related links:

Merseyside WDA

But it is a boost to MWDA's 3.3b Procurement Programme, which will be delivered in three parts – landfill, waste management and recycling, and resource/recovery.

MWDA has applied to Defra for 90m PFI credits for its scheme and a decision is expected this spring.

Register for free to comment

Subscribe to receive our newsletters and to leave comments.

The Blog Box

Back to top

Subscribe to our newsletter

Get the latest waste and recycling news straight to your inbox.

Subscribe

Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.