SITA begins investigation into Tees Valley EfW fire

SITA begins investigation into Tees Valley EfW fire

SITA UK has launched an investigation into the cause of a fire on Sunday (August 30) which has forced it to close its Tees Valley energy-from-waste (EfW) facility at Haverton Hill, near Billingham.

The fire at the plant, which is used to treat residual waste from a number of local authorities in the North-East, started at around 1.10am on Sunday morning, and 10 fire engines initially attended the incident.

The 390,000 tonne-a-year capacity Tees Valley EfW facility has recently has a £70 million third line extension added
The 390,000 tonne-a-year capacity Tees Valley EfW facility has recently has a £70 million third line extension added
The fire was under control by 2am, though two fire engines remained at the plant until 9.30am, and the company has confirmed that the blaze damaged plant and electrical wiring.

A spokeswoman for SITA UK told letsrecycle.com today (September 1) that, while all three lines at the 390,000 tonne-a-year capacity facility were currently out of operation, “early indications” were that line three would be the first to be back up-and-running, “in the next day or do”.

The £70 million, 136,000 tonne-a-year capacity line three is a recent addition to the Tees Valley facility, and is being used to treat waste collected under the company's PFI-funded waste treatment contract with Northumberland county council.

In June 2009, SITA UK revealed that the extension had passed performance tests (see letsrecycle.com story), and the line is scheduled to be officially opened early next month.

Cause

Commenting on the current situation at the facility, the firm's regional manager, Julie Craigie, said: “We are still investigating the cause of the fire, which shorted some electrical and hydraulic equipment in the backroom area of the facility.

“The fire was not in an area where waste was stored and at no time was there any danger that the waste storage area would be affected.

“There were no injuries as a result of the fire and we are awaiting engineer's reports about the level of damage and its impact on operations,” she added.

Ms Craigie described the fire crews who attended the blaze as “brilliant” and said that “their prompt and efficient service ensured that the amount of damage was limited.”

Waste

As well as burning Northumberland county council's waste to produce electricity, the Tees Valley facility also treats up to 230,000 tonnes-a-year of residual waste from Stockton, Redcar & Cleveland, Hartlepool and Middlesbrough councils, using its two original lines that have been operational for 10 years.

Register for free to comment

Subscribe to receive our newsletters and to leave comments.

The Blog Box

Back to top

Subscribe to our newsletter

Get the latest waste and recycling news straight to your inbox.

Subscribe

Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.